To select a hazardous area off grid power solution, I first match the site classification, electrical load, energy source, autonomy requirement, and environmental conditions before choosing equipment. For most remote industrial sites, a practical solution combines solar generation, battery storage, a suitable power-control system, and certified hazardous-area equipment such as LED explosion-proof lights. I do not recommend selecting products from wattage alone, because enclosure protection, temperature limits, installation method, maintenance access, and certification requirements can determine whether a system is suitable. The correct approach is to define the duty profile, calculate energy demand, add a controlled design margin, and then confirm every component against the project specification.
You can find more information on our web, so please take a look.
Remote facilities may not have a reliable grid connection, and extending utility power can involve long cable routes, difficult terrain, or high installation costs. At the same time, hazardous locations may contain flammable gases, vapors, dust, or fibers that require carefully selected electrical equipment. Off grid power therefore has to deliver dependable energy without introducing equipment that is unsuitable for the classified area.
I treat the project as two connected design tasks: the power system must produce and store enough energy, while every field device must be appropriate for its installation zone. A solar-battery package may be technically adequate in a non-hazardous location but require additional separation, protection, or a different equipment arrangement near process equipment. The final decision should be based on the site documentation and the requirements of the authority having jurisdiction.
Before discussing panels, batteries, or lights, I ask for the hazardous-area classification and the applicable certification framework. Depending on the country and project, documentation may refer to zones, divisions, gas or dust groups, temperature classes, equipment protection levels, or standards such as ATEX and IECEx. I do not assume that one marking applies globally, and I recommend verifying the required marking with the project engineer or local compliance authority.
This step prevents a common purchasing error: selecting a product described as “explosion-proof” without confirming whether its actual marking and construction match the site classification. I recommend keeping the classification document, equipment schedule, and supplier technical file together throughout the procurement process. If any requirement is unclear, the responsible electrical or hazardous-area engineer should resolve it before ordering.
I calculate energy demand from the equipment’s actual operating schedule rather than its nameplate power alone. The load list should include LED explosion-proof lights, instruments, wireless gateways, cameras, control panels, heating or ventilation devices, and any periodic loads. For each item, I record rated power, quantity, operating hours, starting behavior, voltage, and whether it operates continuously or intermittently.
| Load information | Example planning value | Why it matters |
|---|---|---|
| Lighting load | 4 × 100 W LED fixtures | Defines continuous electrical demand when all fixtures operate |
| Daily operating period | 10 hours per day | Converts equipment power into daily energy consumption |
| Battery autonomy target | 72 hours | Provides a planning basis for periods of low solar input |
For example, four 100-watt lights operating for 10 hours use 4,000 watt-hours, or 4 kilowatt-hours, before conversion losses and other loads are included. I then add the control equipment and account for inverter, wiring, battery, and temperature-related losses where applicable. A design margin of about 20% to 30% may be considered as a planning allowance, but the final value should follow the project’s engineering standard rather than an arbitrary percentage.
After calculating the load, I compare the available power architectures. Solar photovoltaic generation with battery storage is often considered where sunlight is available and the load is modest, while a hybrid system may combine solar, batteries, and a generator for sites with high demand or extended poor-weather periods. A direct-current architecture can reduce conversion stages for some instrumentation and lighting applications, but the selected voltage must match the equipment and protection design.
I also consider where the batteries, charge controller, inverter, and generator will be installed. It may be preferable to locate energy-conversion equipment outside the classified area and distribute power to correctly specified field devices. This arrangement can simplify equipment selection, but cable length, voltage drop, surge protection, and environmental exposure still require engineering review.
Battery capacity should be based on usable energy, not only the nominal battery rating. I consider the required autonomy, allowable depth of discharge, conversion efficiency, temperature effects, aging allowance, and the consequences of a low-voltage shutdown. A system designed for 72 hours of autonomy must still provide the required critical loads after these factors are applied, not merely when the battery is new and operating at a laboratory temperature.
Link to MASCO
Remote sites also require a practical maintenance plan. I ask how technicians will inspect the battery enclosure, replace components, verify alarms, and respond to abnormal conditions. Where the site is exposed to salt spray, dust, condensation, or extreme temperatures, enclosure construction and thermal management can affect service life and system availability.
For hazardous-area lighting, I define the required illumination task before selecting a fixture. The specification may need to address mounting height, beam distribution, working-plane illumination, glare, color requirements, emergency operation, and temperature range. MASCO can support projects involving LED explosion-proof lights, but I still recommend confirming the required certification marking, electrical rating, photometric data, cable entries, and installation accessories for each project.
I avoid treating lumen output as a substitute for a lighting design. A higher-output fixture does not automatically provide better visibility if the beam is poorly matched to the area or if glare affects operators. For remote sites, I also compare energy consumption, expected operating hours, mounting hardware, driver behavior, and spare-parts availability.
I recommend creating a technical schedule that separates mandatory requirements from preferences. Mandatory items may include hazardous-area marking, input voltage, operating temperature, ingress protection, battery autonomy, communication interfaces, and enclosure materials. Preferences may include remote monitoring, modular construction, quick-connect wiring, dimming, or a particular mounting arrangement.
Supplier documentation should be checked against the schedule line by line. I request datasheets, dimensional drawings, wiring diagrams, installation instructions, certification documents where applicable, battery calculations, and a clear list of exclusions. This process makes it easier to compare technically equivalent offers and identify hidden integration work.
At MASCO, I approach hazardous area off grid power projects by reviewing the application rather than offering a generic product list. I can help organize the load schedule, identify the information needed for hazardous-area equipment selection, and align LED explosion-proof lighting with the proposed power architecture. The final design remains subject to the project engineer’s calculations, local regulations, and the certification requirements specified for the site.
For an initial technical review, I recommend preparing the hazardous-area classification, site location, solar resource information if available, equipment load list, operating hours, autonomy target, ambient conditions, mounting details, and required delivery schedule. These inputs allow a supplier to identify gaps before quotation and reduce the risk of incompatible equipment. They also provide a clearer basis for discussing customization, testing, packaging, spare parts, and after-sales support.
The best hazardous area off grid power solution is the one that satisfies both the energy requirement and the hazardous-area installation requirement. I recommend beginning with a verified site classification and a complete load profile, then evaluating the power architecture, battery autonomy, lighting specification, environmental protection, and maintenance plan together. This sequence helps prevent costly redesigns caused by selecting a battery, inverter, or explosion-proof light in isolation.
For the next step, send MASCO the site classification, load schedule, operating hours, autonomy target, environmental conditions, and preferred voltage. I can then help identify a suitable starting configuration for remote industrial power and LED explosion-proof lighting, while clearly separating confirmed specifications from items that require project-engineering approval.